Station Street Bridge

Advanteering was engaged to deliver a major bridge and road realignment project involving the construction of a new dual-lane concrete bridge adjacent to an existing single-lane timber structure. The works also included the realignment of the road corridor and conversion of the old bridge into a dedicated pedestrian path. The project presented a range of technical and environmental challenges, including high water levels, difficult subgrade conditions, and delayed utility relocations—but was ultimately delivered through innovative in-house solutions, tight cost controls, and efficient site management.
The Project Included:
-
Full closure of the road and self-performance of traffic management duties.
-
Clearing and grubbing of over 20 mature gum trees.
-
Installation of a combi-grid reinforced working platform over saturated subgrade.
-
Preloading and settlement monitoring of the abutment embankment.
-
Installation of Controlled Modulus Columns for ground improvement at Abutment 1.
-
Construction of temporary shoring using second-hand sheet piles and deadman anchors.
-
Construction of deep reinforced concrete foundations for bridge abutments and piers.
-
CFA piling works for bridge supports including pile trimming and cage placement.
-
Construction of retaining walls, headstocks, and pier columns.
-
Installation of three-span precast concrete bridge beams with a 450T crane.
-
Pouring of the 56m long concrete bridge deck in a single early-morning operation.
-
Installation of drainage scuppers and kerbs along the bridge edges.
-
Profiling of the existing road and placement of new pavement layers.
-
Installation of new steel conduit for Telstra services under the bridge.
-
Installation of drainage pits and Gross Pollutant Traps.
-
Spreading and compaction of limestone and crushed rock basecourse.
-
Asphalt surfacing of the new road alignment and approaches.
-
Installation of concrete footpaths and cyclist-compliant balustrades.
-
Construction of rock pitching to abutments and batter slopes.
-
Concrete encapsulation of sheet pile walls for permanent retention.
-
Final landscaping including topsoil placement, log installation and mulch spreading.
Despite a delayed start and demanding site conditions, Advanteering delivered the project ahead of schedule and under budget. The decision to self-perform critical activities, adopt practical design alternatives, and work collaboratively with stakeholders ensured a high-quality outcome that met all safety, environmental, and client expectations.